Because jacking machines are heavy, the working platform must be high-quality, well-compacted, and have adequate site drainage.
During installation, the pile must be monitored for verticality and structural integrity. In Singapore, it is standard practice to maintain a vertical tolerance of 1:100. Piles are typically installed in segments and joined by welding or mechanical joints. For welded joints, non-destructive testing (NDT) is essential to ensure the connection can withstand the intense compressive forces of the jack. Because jacking machines are heavy, the working platform
The downward movement between the initial jack and the re-jack must not exceed 10 mm with a minimum holding time of 30 seconds . Piles are typically installed in segments and joined
Termination is based on both design depth and measurable jacking resistance: Set Definition Termination is based on both design depth and
The following practices are recommended by the GeoSS Guideline on Jacked Piles to ensure quality and safety during construction: :
If a pile penetrates a consolidating soft soil layer, designers must account for a reversal of force (downdrag) when calculating the required jacked load ( Pjcap P sub j